Question 11 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question 11 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question

DRAG DROP - A manufacturer uses route operations and job scheduling.

You use a unique calendar for a conveyor line.

The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns.

You must make a temporary change to the number of hours the resource is available.

You need to adjust the efficiency percentage for the conveyor line calendar.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Actions

Answer Area

Select working times

Apply the new template to the resource's calendar

Select the calendar related to the resource

Create a new working time template

Update the runtime on the routes that use the resource

Change the efficiency percentage on the days that need
the change

Explanations

Actions

Answer Area

Select working times

Create a new working time template

Apply the new template to the resource's calendar

Change the efficiency percentage on the days that need
the change

Select the calendar related to the resource

Apply the new template to the resource's calendar

Create a new working time template

Update the runtime on the routes that use the resource

Change the efficiency percentage on the days that need
the change