Question

HOTSPOT - A company implements Dynamics 365 Supply Chain Management.

You must use functionality in the system for group production runs to prevent downtime and excessive cleaning of the machines on the production line.

You need to set up the system.

Which behaviors should you expect? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Answer Area

Scenario

You set up a coverage time horizon of 120 days, a
sequence time horizon of 60 days, and a campaign
cycle of 30 days.

You set up a sequencing ID for 50 gram, 100 gram, and

200 gram packages. You assign ranking values as 1, 5,
and 10 respectively.

Expected planning behavior

Two complete campaign cycles of 30 days, each within the 60-days
sequencing time horizon.

Three complete campaign cycles of 30 days, each within the 60-
days sequencing time horizon.

One complete campaign cycle of 120 days.

50 gram packets, then 100 gram packets, then 200 gram packets
200 gram packets, then 100 gram packets, then 50 gram packets

Explanations

Answer Area

Scenario

You set up a coverage time horizon of 120 days, a
sequence time horizon of 60 days, and a campaign
cycle of 30 days.

You set up a sequencing ID for 50 gram, 100 gram, and

200 gram packages. You assign ranking values as 1, 5,
and 10 respectively.

Expected planning behavior

Two complete campaign cycles of 30 days, each within the 60-days
sequencing time horizon.

Three complete campaign cycles of 30 days, each within the 60-
days sequencing time horizon.

One complete campaign cycle of 120 days.

50 gram packets, then 100 gram packets, then 200 gram packets
200 gram packets, then 100 gram packets, then 50 gram packets