Question 57 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question 57 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question

DRAG DROP - A manufacturer sends wiring harnesses to a vendor to be soldered to a connector.

You have created the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.

You create separate subcontracting purchase orders to account for the service.

You attempt to add the service item to the BOM.

The system generates an error.

You need to set up a new item model group for the service item.

Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Actions

Create a new item model group and clear
the stocked product option

Add the service item and set the new

inventory model group in the BOM to.
FIFO

Assign the item model group and
select the stocked product option

Create a new item model group and
select the stocked product option

Add the service item to the BOM

Answer Area

©
@

©©