DRAG DROP - A company uses Discreet manufacturing concepts to produce cables.
The company's production scheduler uses internal documents to track issues on in-process production orders.
The production scheduler must group all in-process production orders according to issues.
The scheduler must be able to easily determine issues with production orders.
You need to implement a method to easily identify production orders with issues.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place: