Question 81 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question 81 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question

HOTSPOT - A company implements Dynamics 365 Supply Chain Management.

You run a master plan each week.

You need to resolve the issue in the scenario.

What should you do? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Answer Area

Scenario Action
Production orders do not appear in the | Vv
Production control module Firm the planning production orders

Rerun master planning
Increase the coverage time fence

You must ensure visibility to all resources

during planning processes Edit the plan. Set the Scheduling method to Job scheduling
Increase the coverage time fence on the plan
Assign a higher ranking to the sequence group assigned to items

Explanations