DRAG DROP - A company implements Dynamic 365 for Finance and Operations.

You run the latest master plan.

You observe invalid results.

You need to set up tracing for the master plan.

In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Actions Answer Area

Create a User Defined Node Data Collector Set in Performance Monitor.

Add the keyword MRP to the Keywords property table and add the
location for the log file.

Select the Create data logs and Event trace data check boxes.

Save and close the setup wizard and the start the monitor.

Add the Microsoft-Dynamics AX-Tracing provider to the Event Trace
Providers list.

Explanations

Actions

Create a User Defined Node Data Collector Set in Performance Monitor.

Answer Area

Create a User Defined Node Data Collector Set in Performance Monitor.

Add the keyword MRP to the Keywords property table and add the
location for the log file.

Select the Create data logs and Event trace data check boxes.

Select the Create data logs and Event trace data check boxes.

Add the Microsoft-Dynamics AX-Tracing provider to the Event Trace
Providers list.

Save and close the setup wizard and the start the monitor.

Add the keyword MRP to the Keywords property table and add the
location for the log file.

Add the Microsoft-Dynamics AX-Tracing provider to the Event Trace
Providers list.

Save and close the setup rd and the start the monitor.