Question 22 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question 22 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question

HOTSPOT - A company implements Dynamics 365 Supply Chain Management.

Production orders are generated for products directly from projects.

You create the following production order:

Create production order

IDENTIFICATION GROUPINGS

Production Pool

000006 v
item number Production group

BOM Vv Tv
Name

BOM SETUP

Ledger

INVENTORY DIMENSIONS Item and resource
Site Reservation

MainOffice Vv Manual Vv
Warehouse Release to warehouse
MainOffice Vv Allow partial reservation
PRODUCTION PROJECT

Type Project ID

Standard V 00000224

Quantity Activity number

50.00

Delivery Posting method
4/12/2019 [za Finished item Vy
— FINISHED ITEM

10:00 AM

Category
ROM/ROLITE Projltem.

Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic.

NOTE: Each correct selection is worth one point.

Hot Area:

Answer Area

Question Answer choice
When will costs for product components and labor be Vv
recognized against the project? Item transactions are created when the production order is ended

Item transactions are created when the production order is started
item transactions are created at each step in the production process

The company is using standard cost for several of its Vv
components used in production. What should you change
in the production order?

Change the Posting method to Consumed
Change the Reservation to Automatic
Change the Category to use Subcontract