Question 25 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question 25 of 112 from exam MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

Question

DRAG DROP - A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

Employees spend considerable time cleaning and setting up machines in a specific area between production orders.

You must group production activities to optimize cleaning and set up time.

You need to set up the system.

In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

NOTE: Each correct selection is worth one point.

Select and Place:

Actions

Assign sequence group IDs to resources
and resource groups

Assign sequence IDs to items

Create sequence IDs specifying values and
ranking

Create sequence groups

Answer Area

©
@

©O

Explanations