Change Theme Requirements | PRINCE2 Foundation Exam Prep

Minimum Requirement for Change Theme

Question

Which is a minimum requirement for applying the change theme?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

http://prince2.wiki/Themes#Change_Theme

The change theme in project management is used to manage change requests or modifications to the project's scope, plans, or baselines. It involves identifying, assessing, and implementing changes to project deliverables and processes while keeping the project on track.

Out of the options given, the minimum requirement for applying the change theme is option C, which is to define the project's approach to baselining products.

Baselining products refers to the process of defining and documenting the project's scope, plans, and objectives. It involves creating a baseline or reference point against which the project's progress is measured and any changes are evaluated. The baseline includes the project's scope, schedule, budget, quality criteria, and other relevant information.

Defining the project's approach to baselining products is important for applying the change theme because it establishes a framework for assessing the impact of changes to the project's scope, plans, or baselines. Without a clear baseline, it is difficult to evaluate the impact of proposed changes, which can lead to delays, cost overruns, and other problems.

Option A, to establish a change budget to fund changes in scope, is not a minimum requirement for applying the change theme. It is a best practice for managing changes to the project's scope, but it is not necessary for applying the change theme.

Option B, to appoint the project manager as part of the change authority, is also not a minimum requirement for applying the change theme. The change authority refers to the group of people responsible for evaluating and approving changes to the project. While the project manager may be part of the change authority, it is not necessary for applying the change theme.

Option D, to record every issue that is raised in the issue register, is also not a minimum requirement for applying the change theme. The issue register is a document used to track and manage project issues or problems, but it is not directly related to managing changes to the project's scope, plans, or baselines.