PRINCE2 Foundation Exam: Continued Business Justification

Which Reflects the PRINCE2 Principle of Continued Business Justification?

Question

Which does NOT reflect the PRINCE2 principle of continued business justification?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The PRINCE2 principle of continued business justification emphasizes that a project should be initiated, planned, and executed only if it continues to remain viable and relevant from a business perspective. This principle aims to ensure that projects are aligned with the strategic goals of the organization and provide a positive return on investment.

Based on the options provided, answer D does not reflect the PRINCE2 principle of continued business justification. This is because the principle emphasizes the importance of continuously justifying the existence of the project from a business perspective. If a project can no longer be justified, it should not have been initiated in the first place. Therefore, if a project can no longer be justified, it should not continue, and it should be stopped.

Answer A reflects the principle of continued business justification because it highlights the importance of having a justifiable reason for starting a project. This reason should be linked to the strategic goals of the organization and provide a positive return on investment.

Answer B also reflects the principle of continued business justification because it emphasizes that the business justification should drive decision-making throughout the project's lifecycle. This means that decisions should be made based on whether the project aligns with the strategic goals of the organization and provides a positive return on investment.

Answer C reflects the principle of continued business justification because it emphasizes that if a project is no longer forecast to deliver a financial benefit, it should be stopped. This ensures that projects are continuously evaluated to ensure that they are still aligned with the strategic goals of the organization and provide a positive return on investment.

In summary, the PRINCE2 principle of continued business justification emphasizes the importance of continuously justifying the existence of the project from a business perspective. Answer D does not reflect this principle because it suggests that a project can be justified at one point and then no longer justified later on.