Minimum Requirement for Applying the Plans Theme

Minimum Requirement for Applying the Plans Theme

Question

Which is a minimum requirement for applying the plans theme?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

http://prince2.wiki/Themes#Plans_Theme

The Plans theme in PRINCE2 is concerned with developing and maintaining a plan that outlines the steps required to achieve the project's objectives. It is essential to have a well-defined plan that identifies the resources, activities, and timelines required to achieve the desired outcomes.

The minimum requirement for applying the Plans theme in PRINCE2 is that the project must have at least two management stages. PRINCE2 is a structured approach to project management that divides the project into stages, each with its own objectives, timelines, and deliverables. The project must have a minimum of two management stages to allow for planning and control activities to be carried out effectively.

Option B, stating that the team managers in the project must prepare team plans, is not entirely accurate. Although team plans are an important aspect of project planning, they are not a minimum requirement for applying the Plans theme.

Option C, stating that scope tolerance must be prioritized using MoSCoW, is not accurate either. MoSCoW is a prioritization technique used in PRINCE2 to prioritize requirements based on the Must, Should, Could, and Won't categories. Although it is an important tool for project planning, it is not a minimum requirement for applying the Plans theme.

Option D, stating that the project plan must be presented as a Gantt chart, is also not accurate. A Gantt chart is a useful tool for visualizing the project timeline and activities, but it is not a minimum requirement for applying the Plans theme.

Therefore, the correct answer is A - The project must have at least two management stages.