Which is NOT included in the PRINCE2 definition of a project?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The correct answer is C. A project is NOT part of 'business as usual.'
Explanation: PRINCE2 (PRojects IN Controlled Environments) is a process-based project management methodology that provides a framework for managing projects. It defines a project as a temporary organization created for delivering one or more business products according to an agreed Business Case.
The four components of the PRINCE2 definition of a project are:
A. A project is a temporary organization: A project is a temporary endeavor with a defined start and end date, and a specific scope of work to be delivered.
B. A project's purpose is to deliver one or more business products: The objective of a project is to deliver a product, service, or result that provides value to the business or organization.
C. A project is NOT part of 'business as usual': A project is a separate and distinct entity from the ongoing operations of an organization. It is a temporary initiative that requires a unique set of resources, such as personnel, funding, and equipment.
D. A project is based on an agreed Business Case: A Business Case is a document that outlines the reasons for undertaking the project and the expected benefits and costs.
Therefore, option C is the correct answer, as it contradicts the PRINCE2 definition of a project.