What product defines the reporting requirements between the Project Manager and Team Manager?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The correct answer is D. Work Package.
In project management, a Work Package is a component of the project plan that outlines the work that needs to be done to complete a specific task or deliverable. The Work Package is a key communication tool between the Project Manager and the Team Manager because it outlines the reporting requirements for that specific piece of work.
The Work Package includes details such as the scope of the work, the resources needed to complete the work, the timeline for completing the work, and any constraints or assumptions that should be taken into consideration.
The Project Manager assigns Work Packages to Team Managers who are responsible for ensuring that the work is completed according to the specifications outlined in the Work Package. The Team Manager is also responsible for reporting progress on the work back to the Project Manager, using the reporting requirements outlined in the Work Package.
Therefore, the Work Package is the product that defines the reporting requirements between the Project Manager and Team Manager.