Prince2 Foundation Exam: Missing Words in Project Management Sentence

Identifying the Right Words for Effective Project Management

Question

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

http://prince2.wiki/Directing_a_Project

The missing words in the sentence are related to the responsibility for day-to-day management of the project. This implies that the project manager has a crucial role in overseeing the daily activities of the project and ensuring that everything runs smoothly.

Option A suggests that both the project manager and the project board are responsible for day-to-day management. While the project board may have some oversight responsibilities, it is not typically responsible for day-to-day management. Therefore, this option is not the best answer.

Option B proposes that both the project manager and the team manager(s) are accountable for day-to-day management. While team managers may have some responsibilities for managing their teams' activities, they are not typically responsible for overall project management. Therefore, this option is also not the best answer.

Option C states that the project manager has responsibility for day-to-day management of the project. This is the correct answer since the project manager is the person who is primarily responsible for overseeing the daily activities of the project, ensuring that milestones are met, and coordinating the work of team members.

Option D suggests that the project manager decides who is responsible for day-to-day management. This option is not correct since the project manager is the one who is responsible for day-to-day management, and they do not have the authority to delegate this responsibility to someone else.

In summary, the correct answer is option C, which states that the project manager has responsibility for day-to-day management of the project.