Which is a purpose of the Managing Product Delivery process?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The Managing Product Delivery process is one of the seven processes of PRINCE2, a project management methodology widely used in various industries. This process is executed by the Team Manager(s) under the guidance of the Project Manager and is primarily responsible for delivering the products (i.e., outputs or deliverables) required by the customer or user.
Out of the given options, answer B is the correct purpose of the Managing Product Delivery process, which is to provide a controlled link between the Project Manager and the Team Manager(s). This means that the process enables effective communication and collaboration between these two roles to ensure that the products are delivered according to the agreed quality standards, timescales, and budget. In other words, the Team Manager(s) report progress, issues, and risks to the Project Manager, who provides direction, support, and feedback.
Option A is not a correct purpose of the Managing Product Delivery process, as it describes the purpose of the Work Package process, which is to enable the Senior Supplier to review the success of the current Work Package by providing them with sufficient information from the Project Manager.
Option C is also incorrect as it describes the purpose of the Team Plan process, which is to provide a detailed plan of how the team will create the products, including the schedule, resources, and quality criteria. The Project Board may request updates to the Team Plan, but this is not the primary purpose of the Managing Product Delivery process.
Option D is a vague purpose that does not specifically relate to the Managing Product Delivery process. While it is essential to establish solid foundations for the project, this is achieved through the Starting Up a Project process, which defines the project's objectives, scope, risks, and benefits and ensures that the necessary resources and stakeholders are identified and engaged.
In summary, the correct purpose of the Managing Product Delivery process is to provide a controlled link between the Project Manager and the Team Manager(s) to ensure effective delivery of the required products.