Which is NOT included in the PRINCE2 definition of a project?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
PRINCE2 is a widely used project management framework that provides guidance on project management best practices. According to PRINCE2, a project is defined as a temporary organization that is created to deliver one or more business products based on an agreed Business Case.
The correct answer to the question is C. A project is NOT part of business as usual according to the PRINCE2 definition of a project. Business as usual (BAU) refers to the ongoing operations and activities of an organization that are necessary to maintain its day-to-day operations. In contrast, a project is a temporary endeavor that is created to deliver specific business products or outcomes that are beyond the scope of BAU activities.
Here are detailed explanations of the other options:
A. A project is a temporary organization: This is a correct statement and is included in the PRINCE2 definition of a project. PRINCE2 emphasizes that a project is a temporary organization with a specific objective and a defined lifecycle.
B. A project's purpose is to deliver one or more business products: This is also a correct statement and is included in the PRINCE2 definition of a project. The purpose of a project is to create a product or deliverable that meets the requirements of the business and delivers value to the stakeholders.
D. A project is based on an agreed Business Case: This is a correct statement and is also included in the PRINCE2 definition of a project. The Business Case is a key document that outlines the justification, costs, benefits, and risks associated with the project. PRINCE2 emphasizes that the Business Case should be regularly reviewed and updated throughout the project to ensure that it remains viable and justifiable.