Purpose of Quality Planning | Prince2 Re-Registration Exam

Purpose of Quality Planning

Question

Which is a purpose of quality planning?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

Quality planning is an essential process within project management that focuses on defining and documenting the quality standards and requirements for a project's deliverables. Quality planning ensures that the project's objectives are met and that the final product satisfies the customer's needs and expectations. The main purpose of quality planning is to establish a framework that enables the project team to create and deliver high-quality products.

Option A, "Define the structure of the project management team," is not a purpose of quality planning. While project team structure is important to the success of the project, it is not related to quality planning.

Option B, "Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product," is a correct answer. Quality planning involves defining the acceptance criteria for the project's deliverables, so that the Project Board can agree on the level of quality expected of the product. Acceptance criteria are the measurable and testable requirements that a product must meet in order to be considered acceptable.

Option C, "Document approval records for those project products that have met their quality criteria," is not a purpose of quality planning. This activity is part of the quality control process, which is concerned with monitoring and verifying that the project's deliverables meet the established quality standards.

Option D, "Produce the Project Plan with resource and schedule information," is not a purpose of quality planning. While quality planning is an important part of the project planning process, it is not focused on producing the project plan with resource and schedule information. This activity is part of the project planning process and is concerned with defining the project's scope, objectives, timelines, and resource requirements.

In conclusion, the correct answer is option B. Quality planning is essential to establish the acceptance criteria for the project's deliverables, so that the Project Board can agree on the level of quality expected of the product. This helps the project team to create and deliver high-quality products that satisfy the customer's needs and expectations.