Which is a purpose of the Risk theme?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The purpose of the Risk theme in PRINCE2 methodology is to identify, assess, and control risks that may impact the project objectives. Risks are defined as uncertain events or conditions that, if they occur, may have a positive or negative effect on the project's objectives.
The correct answer to the question is B: Identify, assess, and control problems that have occurred.
The Risk theme is essential because it helps project managers to anticipate and prepare for potential risks that may affect the project. It involves identifying all potential risks, assessing their probability and impact, and creating plans to mitigate or avoid those risks. The Risk theme includes several activities, such as risk identification, risk assessment, risk response planning, and risk monitoring and control.
Answer A is incorrect because although continuous improvement is an essential element of PRINCE2 methodology, it is not the primary purpose of the Risk theme.
Answer C is incorrect because the Risk theme is not focused on time-driven control, but rather on the identification, assessment, and control of risks.
Answer D is also incorrect because although cost-effectiveness is an essential element of PRINCE2 methodology, it is not the primary purpose of the Risk theme.
In summary, the primary purpose of the Risk theme is to identify, assess, and control problems that have occurred, and it is an essential element of PRINCE2 methodology.