Question 62 of 200 from exam PRINCE2-PRACTITIONER: Practitioner Project Management Certification

Question 62 of 200 from exam PRINCE2-PRACTITIONER: Practitioner Project Management Certification

Question

Scenario - Extract from the Project Product Description (with errors)

Composition

1. Monthly calendar displays
2. 100gsm glossy paper

3. Full colour

4. Selected envelope

5. Chosen label design

6. List of customers

7. Selected photos

8. Photo session schedule

Derivation

9. New company logo design
10. Previous calendar designs
11. Intemal creative team

12. Production cost forecast

Development skills
required

13. Photographer
14. Intemal creative team
15. Printer

Customer's quality
expectations

16. Professional photos
17. 10% more calendars should be printed than required to allow
for any late additions to the list of customers

18. Compliance with applicable corporate standards

19. The calendar should reflect the company image

as described in the corporate branding standards

20. The calendar will increase orders by at least 10%
with a minimum of 10 further orders from the list of
prospective customers within 12 months

‘Acceptance
criteria

‘21. Appearance - each photo should be sufficiently attractive and
humorous that the customer wants to display it

22. Appearance - new company logo promotes

strong image

23. Security - complies with Data Protection Act

24. Acouracy - public holidays match the list

supplied by Marketing on 01 November

Which 2 statements apply to the Acceptance criteria section?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

AC.