Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The correct answer is B. Follow-on action recommendations.
When a project is completed, there may be uncompleted work that needs to be done to the project product. This may include items that were identified during the project but were not completed before the project closed or items that were discovered after the project was closed. These items are typically documented in the Follow-on Action Recommendations (FARs) document.
FARs document any actions that need to be taken after the project has closed, but that are not part of the project itself. This may include tasks that were not completed during the project or tasks that were discovered after the project was closed. The document should include a description of each task, why it needs to be done, and who is responsible for completing it.
Off-specifications refer to any work that does not meet the specified requirements of the project. These are typically documented in the Issue Register, along with any other problems or issues that arise during the project.
The Issue Register is a document that tracks all issues and problems that arise during the project. It includes a description of each issue, the impact it has on the project, and any actions taken to resolve it.
The Risk Register is a document that identifies potential risks to the project and outlines strategies to mitigate them. It does not typically include documentation of uncompleted work after the project has closed.
Therefore, the correct answer to this question is B. Follow-on action recommendations.