Question

A software development project is struggling with a certain technology that is unknown to the project team.

A project manager has received a third-party proposal to transfer the risk.

Which of the following should the project manager do NEXT?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

E.

The project manager is facing a challenge with a particular technology that the project team is unfamiliar with. The manager has received a third-party proposal to transfer the risk.

In this context, "transfer the risk" means outsourcing the work related to that technology to a third-party vendor who has the expertise to handle it. This can be an effective risk management strategy, but it requires careful consideration.

The next step for the project manager should be to issue a Request for Proposal (RFP). An RFP is a document that outlines the project's requirements and asks potential vendors to submit a proposal that outlines how they would meet those requirements.

By issuing an RFP, the project manager can solicit bids from multiple vendors, compare their offerings, and select the vendor that best meets the project's needs. This process can help ensure that the project team gets the best possible value for their money while also mitigating the risk of working with an unknown technology.

An RF1 (Request for Information) is a preliminary document that seeks to gather information from potential vendors about their products and services. An RFQ (Request for Quote) is a document that asks vendors to provide a quote for a specific product or service. These documents may be useful in some contexts, but in this case, an RFP is the appropriate next step.

A change request is a document that outlines a proposed change to the project's scope, schedule, or budget. While the project manager may need to make changes to accommodate the use of a third-party vendor, issuing a change request is not the next step in this process.

Similarly, a request for bid is not the appropriate next step. This term is not commonly used in project management and may be confusing. The correct term is Request for Proposal (RFP).