The project's network map has a loop with multiple project outcomes.
This is the result of which of the following scheduling tools?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The situation described in the question, where a project's network map has a loop with multiple project outcomes, indicates the presence of a "feedback loop" in the project network diagram. This situation can occur when a project activity is dependent on itself or other activities that depend on it. As a result, the activity can be rescheduled, leading to multiple project outcomes.
The scheduling tools mentioned in the answers are all techniques used to plan and manage project schedules. Here's a brief explanation of each of the tools:
A. Establishing project schedule baselines: This is the process of setting a project's performance measures, such as time, cost, and scope, as a reference point to track progress and performance. Schedule baselines help project managers to identify deviations from the planned schedule and take corrective action.
B. Critical Path Analysis: This is a technique used to identify the critical path in a project's network diagram. The critical path is the longest sequence of activities that determines the project's duration. Activities on the critical path have no slack time, which means any delay in completing them will delay the project's overall completion time.
C. Critical Chain Method: This is a technique used to manage uncertainties and contingencies in project schedules. The critical chain method identifies and manages the critical path's resources and buffers to protect the project's completion time against delays.
D. Graphical evaluation and review technique (GERT): This is a technique used to model uncertain events and their potential impacts on a project's schedule. GERT diagrams can represent events and decisions that can affect project schedules and their probabilities.
Of the four scheduling tools mentioned, the most likely one to result in a loop with multiple project outcomes is the Critical Chain Method (C). This is because the critical chain method involves identifying and managing the critical path's resources and buffers, which can result in multiple outcomes depending on how the resources and buffers are managed. However, it is worth noting that a loop with multiple project outcomes can also occur in other scheduling tools, such as GERT.