CompTIA Project+ Exam: Negative Slack in Project Status Report

Negative Slack in Project Status Report

Question

In the review of a project status report, the slack is negative.

Which of the following should the project manager tell the stakeholders?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

The term "slack" refers to the amount of time that an activity or task can be delayed without delaying the entire project. Negative slack, therefore, means that the project is behind schedule.

Option A, "The project is behind schedule," is the correct answer to this question. The project manager should inform stakeholders that the project is behind schedule and that corrective action is required to get the project back on track.

Option B, "The project is over budget," is not relevant to the issue of negative slack. While cost overruns may be a concern for stakeholders, this is not the issue being addressed by negative slack.

Option C, "The project has float available," is also not relevant to negative slack. Float refers to the amount of time an activity can be delayed without delaying the project's overall completion date. While float can be a useful tool for managing a project schedule, it is not the issue being addressed by negative slack.

Option D, "The project needs a gate review," is also not relevant to negative slack. A gate review is a project management process that occurs at various stages of a project and is used to determine whether the project should continue to move forward. While a gate review may be necessary for some projects, it is not related to the issue of negative slack.

In summary, the correct answer is A: The project is behind schedule. The project manager should inform stakeholders of the delay and take corrective action to get the project back on track.