Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management.
It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."
Click on the arrows to vote for the correct answer
A. B. C. D.A.
The document described in the statement is the Risk Management Plan. The Risk Management Plan is a document developed during the risk management process that outlines how risks will be identified, assessed, and managed throughout the project or program.
The Risk Management Plan includes the results of the qualitative and quantitative risk analyses, as well as the risk response planning. The qualitative risk analysis involves a subjective assessment of the likelihood and impact of identified risks, while the quantitative risk analysis involves a more objective assessment of risk through numerical analysis. The risk response planning outlines how the organization will respond to identified risks, including risk avoidance, risk mitigation, risk transfer, and risk acceptance.
The Risk Management Plan is a critical component of the risk management process, as it helps to ensure that risks are identified and addressed in a timely and effective manner. It is typically developed early in the project or program, and is updated throughout the project lifecycle as new risks are identified or existing risks change.
The other options listed in the question do not fit the description provided. The Risk Register is a document used to track identified risks and their status, but it does not contain the results of the qualitative and quantitative risk analyses or the risk response planning. The Project Charter is a document that outlines the objectives, scope, and stakeholders of a project, but it is not specifically related to risk management. The Quality Management Plan is a document that outlines how quality will be managed throughout a project or program, but it does not specifically address risk management.