There are seven risks responses that a project manager can choose from.
Which risk response is appropriate for both positive and negative risk events?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
The seven risk responses are as follows:
Of these options, the risk response that is appropriate for both positive and negative risk events is Acceptance (option A). Acceptance is appropriate for both positive and negative events because it involves acknowledging the risk and making a conscious decision not to take action to address it.
In the case of a negative risk event, accepting the risk may be appropriate if the cost or effort required to mitigate or avoid the risk is greater than the potential impact of the risk. In the case of a positive risk event, accepting the risk may be appropriate if the potential benefit of exploiting or enhancing the opportunity is not worth the cost or effort required to do so.
Mitigation (option B), sharing (option C), and transference (option D) are all appropriate for negative risk events, as they involve taking action to address the risk or transfer it to another party. Exploiting (option F) and enhancing (option G) are appropriate for positive risk events, as they involve taking action to maximize the potential benefit of the opportunity.