The shortest time to recovery method in the event of a complete datacenter failure is to utilize a:
Click on the arrows to vote for the correct answer
A. B. C. D. E.B.
In the event of a complete datacenter failure, a quick recovery is crucial to avoid extended periods of downtime that can be costly to an organization.
A warm site, hot site, and cold site are disaster recovery options that can be used to achieve a quick recovery.
A cold site is a backup datacenter that has the necessary infrastructure, such as power and cooling, but does not have the equipment or data necessary to run the organization's operations. In this scenario, the organization would need to restore its data from backups, install and configure the necessary hardware and software, and then resume operations. The recovery time for a cold site can be days or even weeks.
A warm site is a backup datacenter that has the necessary infrastructure, as well as some of the organization's hardware and data, but not all of it. In this scenario, the organization would need to restore its data from backups, install and configure any missing hardware and software, and then resume operations. The recovery time for a warm site can be faster than a cold site, but still days or even hours.
A hot site is a backup datacenter that has the necessary infrastructure, hardware, and data to immediately resume operations in the event of a datacenter failure. In this scenario, the organization's data is continuously replicated to the hot site, so there is no need to restore data or install and configure hardware and software. The recovery time for a hot site is the shortest of the three disaster recovery options, typically measured in minutes or even seconds.
Therefore, the correct answer to the question is B. hot site, as it is the disaster recovery option that provides the shortest time to recovery in the event of a complete datacenter failure.