You are a Solution Architect and planning the go-live with a new solution.
What are three activities you should perform just before to go-live?
Click on the arrows to vote for the correct answer
A. B. C. D. E.Correct Answers: A, B and D
Before you can go-live with a Power Platform solution, you need to conduct the set of proper tests.
A Solution Architect takes part in testing by providing directions for the test and development teams, triaging problems from testing, and participating in go-live planning and implementation.
There are several types of common tests for Power Platform projects.
They include unit, functional, acceptance, regression, integration, security, performance, disaster recovery, etc.
A Solution Architect and the team should define the types and scope of appropriate tests.
After the main volume of tests is done, a Solution Architect needs to perform several activities before implementing the go-live strategy: Performance testing - ensuring that solution performance is within established parameters.
Deployment planning - includes plan and activities before go-live deployment.
Risk assessment - additional solution examination for possible points of failure.
All other options are incorrect.
For more information about the go-live preparation activities, please visit the below URLs:
As a Solution Architect, there are several critical activities that should be performed just before going live with a new solution. Here are the explanations of the three most important activities from the list provided:
User Acceptance Testing: User acceptance testing (UAT) is a critical activity that should be performed just before the go-live phase. UAT helps ensure that the solution meets the needs and expectations of end-users. During UAT, real users are asked to perform various tasks within the solution, and their feedback is collected and analyzed. Any issues or concerns that are identified during UAT can be addressed before the solution goes live, helping to ensure a successful launch.
Deployment Planning: Deployment planning is another essential activity that should be performed just before the go-live phase. Deployment planning involves creating a detailed plan that outlines how the solution will be deployed and implemented. This plan should include information on how the solution will be rolled out to users, the steps that will be taken to ensure that the solution is properly configured, and any necessary data migrations or integrations. A well-designed deployment plan can help ensure that the solution is launched smoothly and with minimal disruption to users.
Risk Assessment: Risk assessment is the process of identifying potential risks and issues that could impact the success of the solution. This activity should be performed just before the go-live phase to ensure that any potential risks or issues are identified and addressed before the solution is launched. During risk assessment, potential risks are identified and evaluated, and mitigation strategies are developed to address them. This can include things like creating contingency plans for potential issues, developing backup and recovery plans, and ensuring that security measures are in place to protect the solution and its data.
In addition to these three activities, it is also essential to perform performance testing and security testing just before the go-live phase. Performance testing can help ensure that the solution can handle the expected workload and that it performs optimally, while security testing can help identify any vulnerabilities or weaknesses in the solution's security measures. By performing these critical activities just before the go-live phase, Solution Architects can help ensure that the solution is ready for launch and that it will be successful in meeting the needs of end-users.