Impact of Abrupt Resignation on Project Workload

Question

A senior developer abruptly resigned without notice.

Because of the senior developer's expertise, the active task workload was substantial.

This would likely impact the project's: (Choose two.)

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E. F.

BD.

The sudden resignation of a senior developer without notice can have significant impacts on a project, including affecting the workload and potentially impacting various aspects of the project. The two project areas that are likely to be impacted the most due to the sudden departure of the senior developer are:

  1. Scheduling: The sudden departure of a senior developer can lead to delays in the project schedule, as the remaining team members may not have the required skills and experience to complete the tasks. The new team members may need additional time to learn the existing code and familiarize themselves with the project, which may cause delays in the completion of the project. Moreover, it may be difficult to find a replacement for a senior developer, which can cause further delays.

  2. Quality: The senior developer was likely responsible for ensuring that the code produced by the team met the required quality standards. Without the senior developer's oversight, there may be an increased risk of errors, bugs, and other quality issues in the code. As a result, the quality of the project may suffer, and additional resources may be required to fix any issues that arise.

While the remaining project areas (environment, requirements, scope, and budget) could also be impacted by the sudden departure of a senior developer, scheduling and quality are the two areas that are likely to be affected the most. The impact on these areas can result in project delays, increased costs, and a reduced ability to deliver a quality product.