Change Control Process

Change Control Process

Question

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The change management system is comprised of several components that guide the change request through the process.

When a change request is made that will affect the project scope.

The Configuration Management System evaluates the change request and documents the features and functions of the change on the project scope.

The component of the change management system responsible for evaluating, testing, and documenting changes created to the project scope is the Integrated Change Control process.

Integrated Change Control is a critical part of project management that deals with handling changes to the project scope, schedule, and cost. This process is responsible for ensuring that all changes are evaluated, tested, and documented before they are approved and implemented.

The Integrated Change Control process typically involves a Change Control Board (CCB), which is responsible for reviewing and approving or rejecting all change requests. The CCB includes key stakeholders such as project sponsors, project managers, and subject matter experts.

Once a change request is received, the CCB evaluates its impact on the project scope, schedule, and cost. This evaluation involves reviewing the project plan, determining the feasibility of the change, and assessing the potential risks and benefits of the change.

If the change request is approved, it is then tested to ensure that it does not cause any adverse effects on the project. The results of the testing are documented to provide a record of the testing process and its outcome.

The Integrated Change Control process also involves updating the project documentation to reflect the approved changes. This includes updating the project scope, schedule, and cost estimates to reflect the impact of the change.

In summary, the Integrated Change Control process is responsible for evaluating, testing, and documenting changes created to the project scope. This process is critical to ensure that changes are carefully considered, thoroughly tested, and properly documented to minimize the risks associated with change.