Walter is the project manager of a large construction project.
He'll be working with several vendors on the project.
Vendors will be providing materials and labor for several parts of the project.
Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team.
Stakeholders for the project have added new requirements, which have caused new risks in the project.
A vendor has identified a new risk that could affect the project if it comes into fruition.
Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk.
What should Walter also update in this scenario considering the risk event?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
In this scenario, Walter has identified a new risk that could affect the project if it comes into fruition. He has updated the risk register and created potential risk responses to mitigate the risk. However, it is also important to consider other project management documents that may need to be updated based on the risk event.
Option A: Project management plan The project management plan is a comprehensive document that outlines how the project will be executed, monitored, and controlled. It includes the project scope, schedule, budget, quality management plan, risk management plan, and other key project management components. If the risk event impacts any of these components, then the project management plan should be updated accordingly. For example, if the risk event impacts the project schedule, then the schedule baseline may need to be updated to reflect the new timeline.
Option B: Project contractual relationship with the vendor Since Walter is working with several vendors on the project, it is important to consider the contractual relationships with the vendors. The new risk event may impact the vendor's ability to deliver on their contractual obligations or may require new contractual agreements. Therefore, the project contractual relationships with the vendor should be reviewed and updated accordingly.
Option C: Project communications plan The project communications plan outlines how information will be communicated to stakeholders throughout the project. If the risk event impacts the project in a way that requires changes to the project communications plan, then it should be updated. For example, if the risk event impacts the project budget, then the communications plan may need to be updated to include new budget information.
Option D: Project scope statement The project scope statement outlines what work will be performed on the project and what is out of scope. If the risk event impacts the project scope, then the scope statement should be updated accordingly. For example, if the risk event requires additional work to be performed, then the scope statement may need to be updated to include the new work.
In summary, all of the options A to D could potentially need to be updated depending on the impact of the risk event. However, the most critical document to update in this scenario would be the project management plan, as it provides a comprehensive view of the project and outlines how it will be executed, monitored, and controlled.