Question

Thomas is a key stakeholder in your project.

Thomas has requested several changes to the project scope for the project you are managing.

Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope.

The change control board agrees with you.

What component of the change control system communicates the approval or denial of a proposed change request?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

The component of the change control system that communicates the approval or denial of a proposed change request is the Integrated Change Control.

Integrated Change Control is a process that brings together all the components of change control in a coordinated and standardized manner. It ensures that changes are properly identified, evaluated, approved or rejected, and implemented. The process involves various activities, including identifying and documenting the proposed changes, analyzing the impacts of the changes, reviewing and approving or rejecting the changes, and tracking the changes throughout the project.

In this scenario, Thomas, a key stakeholder, has requested several changes to the project scope. Upon review of the proposed changes, it was discovered that the new requirements are laden with risks, and the project manager recommended to the change control board that the changes be excluded from the project scope. The change control board agreed with the recommendation and communicated the approval or denial of the proposed change request through the Integrated Change Control process.

The other options listed are also important components of the change control system, but they do not directly communicate the approval or denial of a proposed change request. The Configuration Management System is a system that identifies, organizes, and controls the configurations of the project's components. The Change Log is a document that records all the changes made to the project, including the status of the changes, who requested them, who approved them, and when they were implemented. The Scope Change Control System is a subset of the overall change control system that specifically focuses on managing changes to the project scope. However, none of these components directly communicate the approval or denial of a proposed change request.