Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours.
Should this machine overheat even once it will delay the project's end date.
You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down.
The temperature of 430 is called what?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The temperature of 430 degrees Fahrenheit in this scenario is called a "risk trigger."
A risk trigger is an event or condition that indicates the occurrence of a risk. In this case, the risk is that the machine could overheat and cause a delay in the project's end date. The trigger is the temperature of 430 degrees Fahrenheit, which is considered a critical threshold that could lead to the risk event occurring.
Once the risk trigger is identified, the project team can develop a risk response plan to mitigate or avoid the risk event. In this case, the risk response is to pause the machine for at least an hour to cool it down once the temperature reaches 430 degrees Fahrenheit. By doing so, the team can prevent the machine from reaching the critical threshold of 450 degrees Fahrenheit, which would trigger the risk event of the machine overheating and shutting down for 48 hours.
Overall, identifying risk triggers is an essential step in managing risks effectively. By anticipating potential risks and identifying their triggers, organizations can develop risk response plans and take proactive measures to minimize the impact of the risks.