Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours.
Should this machine overheat even once it will delay the project's end date.
You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down.
The temperature of 430 is called what?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The correct answer is C. Risk trigger.
A risk trigger is an event, condition or situation that can indicate that a risk is about to occur or has occurred. In this case, the trigger is the temperature reaching 430 degrees Fahrenheit, which indicates that the machine is at risk of overheating and potentially causing a delay in the project's end date.
Identifying the risk trigger and creating a response plan to mitigate the risk is an important part of risk management. By pausing the machine at 430 degrees to cool it down, the team is taking proactive steps to prevent the machine from overheating and potentially causing a delay in the project's completion.
Risk identification is the process of identifying potential risks that may impact the project, while risk response is the process of developing strategies to manage those risks. A risk event is an occurrence that results in a negative impact on the project, such as the machine overheating and causing a delay in the project's completion.
Therefore, the trigger event that is being identified is a potential risk, and the response plan is being created to prevent the risk event from happening. This is why the correct answer is C, risk trigger.