Question

A software development manager is taking over an existing software development project.

The team currently suffers from poor communication due to a long delay between requirements documentation and feature delivery.

This gap is resulting in an above average number of security-related bugs making it into production.

Which of the following development methodologies is the team MOST likely using now?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

Based on the scenario provided, the team is suffering from poor communication, a long delay between requirements documentation and feature delivery, and an above-average number of security-related bugs making it into production. These issues suggest that the team is likely using a Waterfall development methodology.

Waterfall is a sequential development methodology that involves a linear, step-by-step approach to software development. It typically includes distinct phases such as requirements gathering, design, implementation, testing, and maintenance. Each phase must be completed before the next can begin, and the process is generally inflexible.

The scenario describes a long delay between requirements documentation and feature delivery, which is characteristic of Waterfall development. In a Waterfall approach, requirements are typically defined at the beginning of the project and documented in detail before any development work begins. This can lead to delays in feature delivery since all requirements must be completed before development can begin.

Additionally, the scenario mentions that there is an above-average number of security-related bugs making it into production. This can be attributed to the inflexibility of the Waterfall approach, which may not allow for changes or adjustments to be made easily once development has progressed past a certain point. This can result in security vulnerabilities being missed or overlooked until later stages of development, when they are more difficult and costly to fix.

In contrast, Agile and Scrum methodologies are more iterative and flexible. They focus on delivering features in smaller, more frequent increments, allowing for more frequent feedback and adjustments to be made throughout the development process. This approach can help to reduce delays and catch security issues earlier in the development cycle.

Spiral methodology is a risk-driven approach that combines elements of both Waterfall and Agile methodologies. It is typically used for large, complex projects that require a high level of risk management. However, based on the scenario provided, it is less likely that the team is using Spiral methodology since it does not directly address the communication and security issues mentioned in the scenario.

In summary, based on the poor communication, long delays, and security-related bugs described in the scenario, the team is most likely using a Waterfall development methodology.