Superior Project Selection: Replacement Chain Approach

Project A vs. Project B: NPV and IRR Comparison

Prev Question Next Question

Question

Intelligent Semiconductor, a diversified technology company, is considering two mutually-exclusive projects. Assume the following information:

Project A -

Initial cash outlay: ($500,000)

t1: $125,000

t2: $125,000

t3: $155,000

t4: $285,000

Cost of capital 11.35%

Project B -

Initial cash outlay ($395,000)

t1: $170,000

t2: $160,000

t3: $175,000

Cost of capital 11.35%

Assuming no taxes, a $0.00 salvage value at the end of each projects' life, and the ability for each project to be replicated identically, identify the superior project according to the Replacement Chain approach. Additionally, what is the NPV and IRR of the superior project over the common life?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E. F.

Explanation

The Replacement Chain, or "Common Life" approach, is a useful analysis method which allows two or more projects with unequal lives to be examined. In the

Replacement Chain approach, the lifespans of each project being examined are multiplied in such a way that the resulting projects share a "common life." In this example, Project A has a lifespan of 4 periods, whereas Project B has a lifespan of 3. The common multiple of both is 12, and to transform each project into one which has a twelve period lifespan, multiply project A by 3 and Project B by 4. Doing so will result in the following series of cash flows for Project A:

Project A -

t0 ($500,000)

t1: $125,000

t2: $125,000

t3: $155,000

t4: [$285,000 + ($500,000)]=($215,000)

t5: $125,000

t6: $125,000

t7: $155,000

t8: [$285,000 + ($500,000)]=($215,000)

t9: $125,000

t10 $125,000

t11: $155,000

t12: $285,000

Multiplying project B by 4 will result in the following cash flows: t0 ($395,000) t1: $170,000 t2: $160,000 t3: [$175,000 + ($395,000)]=($220,000) t4: $170,000 t5: $160,000 t6: [$175,000 + ($395,000)]=($220,000) t7: $170,000 t8: $160,000 t9: [$175,000 + ($395,000)]=($220,000) t10: $170,000 t11: $160,000 t12 $175,000

Solving for NPV and IRR will determine that Project B is superior on both figures, with an NPV of $35,417.16, and an IRR of 13.301%. Project A has a NPV of

$22,256.14 and an IRR of 12.22%.