Consider the following three projects:
Project A -
Initial cash outflow: $1,000,000
Cash inflows as follows -
t1: $500,000
t2: $450,000
t3: $150,000
t4: $150,000
t5: $150,000
Project B -
Initial cash outflow: $1,000,000
Cash inflows as follows -
t1: $150,000
t2: $150,000
t3: $150,000
t4: $450,000
t5: $500,000
Project C -
Initial cash outflow $1,000,000 -
Cash inflows as follows -
t1: $280,000
t2: $280,000
t3: $280,000
t4: $280,000
t5: $280,000
Assuming no taxes, an 8.5% cost of capital, along with a $0.00 salvage value at the end of the fifth year, what is the NPV of each project? Additionally, which of the three projects has the steepest NPV profile?
Click on the arrows to vote for the correct answer
A. B. C. D. E. F.C
Due to the fact that project B is characterized by having the majority of its cash inflows occurring during later time periods, it is more sensitive to changes in the cost of capital. This fact is exemplified by a steeper NPV profile.