Question 313 of 350 from exam PK0-004: CompTIA Project+

Question 313 of 350 from exam PK0-004: CompTIA Project+

Question

The following tasks are required to complete an IT project that is behind schedule:

ID Task Duration Successors
1 Load servers 5 days 4

2 Configure circuit 8 days 4

3 Finalize MOU 3 days 2,1

4

Create user materials

4 days

Which of the following is the critical path?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.