Which is an objective of the 'managing product delivery' process?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
The objective of the Managing Product Delivery process is to ensure that: Products assigned to the team are authorized and agreed upon.
https://prince2.wiki/processes/managing-product-delivery/The objective of the Managing Product Delivery process is to control and monitor the progress of work packages assigned to the team responsible for delivering the project's products. The process is executed by the team manager, who is accountable for ensuring that the team delivers the required products to the agreed quality, time, and cost.
To elaborate on the answer choices: A. To authorize the work package allocated to the team - This is incorrect because the work package is authorized during the Initiating a Project process and is not the objective of Managing Product Delivery. B. To raise exception reports when tolerance is exceeded - This is partially correct. Managing Product Delivery involves monitoring the progress of work packages against agreed tolerances, and if any deviations occur, the team manager raises an exception report to the Project Manager to take appropriate action. However, this is not the primary objective of the process. C. To ensure that delivered products match expectations - This is partially correct. The team manager ensures that the delivered products meet the required quality standards and match the expectations of the customer. However, this is not the primary objective of the process. D. To record any lessons to help later management stages - This is partially correct. Managing Product Delivery involves capturing any lessons learned during the process and recording them for future reference. However, this is not the primary objective of the process.
In summary, the correct answer is B. To raise exception reports when tolerance is exceeded, as this is one of the primary objectives of the Managing Product Delivery process.