Monitoring and Controlling Project Risks: Inputs for Risk Management Process

Inputs for Monitoring and Controlling Project Risks

Prev Question Next Question

Question

There are four inputs to the Monitoring and Controlling Project Risks process.

Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

Change requests are not one of the four inputs to the Risk Monitoring and Controlling Process.

The four inputs are the risk register, the project management plan, work performance information, and performance reports.

Incorrect Answers: A, B, C: These are the valid inputs to the Risk Monitoring and Controlling Process.

The Monitoring and Controlling Project Risks process is a crucial aspect of project management, as it involves tracking, reviewing, and controlling the risks that may affect the project's objectives. The four inputs to this process are:

A. Risk register: A document that contains all identified risks, their descriptions, potential impacts, and response plans.

B. Work Performance Information: Data that reflects how well the project is progressing and whether the work is being executed according to the project plan.

C. Project management plan: A comprehensive document that outlines the project's objectives, scope, timeline, and resources required to complete it.

D. Change requests: Requests to change the project's scope, timeline, or other parameters.

Out of these four inputs, the one that will NOT help the project manager to prepare for risk monitoring and controlling is likely to be the work performance information. While this information is essential for monitoring the project's progress, it does not directly relate to the identification, analysis, or response to project risks.

In contrast, the other three inputs are critical for effective risk management. The risk register contains all the identified risks, which are the foundation of the monitoring and controlling process. The project management plan outlines the project's objectives and scope, which are essential in determining the potential risks that could affect the project. Finally, change requests may introduce new risks or alter existing ones, making them crucial in the monitoring and controlling process.

In summary, all four inputs are important for effective risk monitoring and controlling, but the work performance information is likely the least relevant of the four in terms of preparing for risk management activities.