CRISC Exam Preparation: Qualitative Risk Analysis Activity

Which one of the following will NOT help Wendy to perform this project management activity?

Prev Question Next Question

Question

Wendy is about to perform qualitative risk analysis on the identified risks within her project.

Which one of the following will NOT help Wendy to perform this project management activity?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

D.

The stakeholder register is not an input to the qualitative risk analysis process.

The four inputs are the risk register, risk management plan, project scope statement, and organizational process assets.

Incorrect Answers: A: The Risk management plan is an input to the risk qualitative analysis process.

B: The project scope statement is needed to help with qualitative risk analysis.

C: The risk register can help Wendy to perform qualitative risk analysis.

To perform qualitative risk analysis, Wendy needs several inputs to perform this project management activity. These inputs include the risk management plan, project scope statement, risk register, and stakeholder register. All of these inputs are essential to perform qualitative risk analysis, except one. The answer is option D, the stakeholder register.

A stakeholder register is a document that identifies all stakeholders involved in a project. This document includes the stakeholders' contact information, roles and responsibilities, and their level of interest and influence on the project. However, it is not directly related to risk analysis. It is mainly used to manage stakeholders' expectations and engagement during the project lifecycle.

On the other hand, a risk management plan provides an overview of the project's risk management process, including risk identification, risk analysis, risk response planning, and risk monitoring and control. The project scope statement outlines the project's objectives, deliverables, and constraints. The risk register, which is a record of all identified risks, including their probability, impact, and risk response plans, is also critical for qualitative risk analysis.

In conclusion, while all of these inputs are essential to perform qualitative risk analysis, the stakeholder register is not directly related to this project management activity.