Which is the purpose of the Change theme?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The Change theme in PRINCE2 project management methodology is concerned with identifying, assessing, and controlling any potential and approved changes to baselined products. The purpose of the Change theme is to ensure that changes to the project's products are made in a controlled and consistent manner, so that the project objectives are achieved without compromising the quality, scope, schedule, or budget.
Option A, "To prevent change to baselined products" is incorrect, as it does not reflect the purpose of the Change theme. In fact, the Change theme is concerned with managing changes to baselined products, not preventing them.
Option B, "To identify, assess and control any potential and approved changes to baselined products" is the correct answer. This option reflects the main purpose of the Change theme, which is to ensure that changes are identified, assessed for impact, and controlled through a formal process.
Option C, "To establish mechanisms to monitor and compare actual achievements against those planned" is incorrect, as it refers to the purpose of the Progress theme, which is concerned with monitoring, reviewing, and reporting the progress of the project against the plan.
Option D, "To assess and control uncertainty" is also incorrect, as it does not reflect the purpose of the Change theme. Although the Change theme can help to manage uncertainty, it is not its primary purpose.