Which are advantages of a clear end to a project? 1

No further costs will be incurred by the project 2

Project products will be transferred to operations and support 3

All benefits will have been achieved 4

The project brief will be re-baselined.

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

http://prince2.wiki/Closing_a_Project

The correct answer is D. 1 and 4.

Here is a detailed explanation of each advantage:

  1. No further costs will be incurred by the project: One of the main advantages of having a clear end to a project is that no further costs will be incurred. This is because once the project is completed, all the tasks and activities associated with it will have been finished, and there will be no need for any additional expenditures related to the project.

  2. Project products will be transferred to operations and support: While this may be true, this option is not included in the answer choices, so it is not applicable in this case.

  3. All benefits will have been achieved: This statement is not necessarily true. Although all the project objectives may have been met, it is possible that some of the benefits will not be realized until some time after the project has been completed. Therefore, this advantage is not directly related to having a clear end to a project.

  4. The project brief will be re-baselined: This is another advantage of having a clear end to a project. By re-baselining the project brief, the team can capture any changes that were made during the project and update the project documentation to reflect the actual results. This can be helpful for future projects, as it provides a reference point for what was accomplished and what was learned.

In summary, the main advantages of having a clear end to a project are that no further costs will be incurred and the project brief will be re-baselined.