Which is a purpose of the 'controlling a stage' process?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
http://prince2.wiki/Controlling_a_Stage#PurposeThe controlling a stage
process is a vital process within the PRINCE2 project management methodology. The primary purpose of this process is to monitor the progress of the current stage and take corrective actions if there are any deviations from the plan, ensuring that the project remains on track to achieve its objectives.
Out of the given options, option B is the correct answer because it accurately describes the purpose of the controlling a stage
process. When a deviation is identified, the project manager must take corrective actions within the agreed-upon tolerance levels to bring the project back on track. This process involves identifying the root cause of the deviation and implementing corrective actions to address it. It also includes updating the project plan and stage plan to reflect the actual progress of the project.
Option A is incorrect because producing a team plan is the responsibility of the team manager, not the controlling a stage
process. Option C is incorrect because obtaining approvals for products delivered in a work package is the responsibility of the managing product delivery
process, not the controlling a stage
process. Option D is also incorrect because updating the project plan to incorporate actuals is the responsibility of the managing a stage boundary
process, not the controlling a stage
process.
In summary, the purpose of the controlling a stage
process is to monitor progress, identify deviations, take corrective actions within tolerance, and update the project plan and stage plan to reflect the actual progress of the project.