PRINCE2 (PRojects IN Controlled Environments) is a widely used project management framework that provides a structured approach to project management. It is divided into three levels of planning:

  1. Project Level Planning
  2. Stage Level Planning
  3. Team Level Planning

Each of these planning levels has a specific purpose and set of deliverables.

A. Benefits Review Plan is not one of the levels of plan in PRINCE2. It is a separate plan that is created during the initiation stage of the project and outlines the benefits that the project is expected to deliver.

B. Programme Plan is not one of the levels of plan in PRINCE2. It is a plan that is created at the program level, which is a group of related projects that are managed together to achieve strategic objectives.

C. Team Plan is not one of the levels of plan in PRINCE2. It is a plan that is created at the team level, which is responsible for delivering specific project outputs.

D. Project Brief is a document that provides a high-level overview of the project and is used to initiate the project. It is not one of the levels of plan in PRINCE2.

The three levels of plan in PRINCE2 are:

  1. Project Level Planning: This is the highest level of planning and involves creating a Project Plan, which outlines the overall scope, objectives, timeline, resources, and risks associated with the project. It is created during the initiation stage of the project and is updated throughout the project lifecycle.

  2. Stage Level Planning: This level of planning involves creating a Stage Plan, which outlines the detailed plan for each stage of the project. It is created during the planning phase of each stage and is used to manage the delivery of specific outputs.

  3. Team Level Planning: This level of planning involves creating a Work Package, which is a detailed plan for a specific task or activity. It is created by the team responsible for delivering the task or activity and is used to manage the delivery of the task or activity.