Which is a purpose of a Project Brief?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
The correct answer is D. Provide a solid basis for the initiation of the project.
A project brief is a document that outlines the objectives, scope, and key deliverables of a project. It is used to provide a solid basis for the initiation of the project by ensuring that all stakeholders have a common understanding of the project's goals, scope, and constraints. The project brief is usually created during the pre-project stage and is used as a reference document throughout the project's lifecycle.
Option A is incorrect because the project mandate is the document that provides the project manager with the authority to begin work on a project. The project brief is created after the project mandate and is used to provide more detail about the project's objectives, scope, and deliverables.
Option B is incorrect because the reporting requirements of the various layers of management involved with the project are typically outlined in the project management plan, not the project brief.
Option C is incorrect because the control of changes to products is typically outlined in the project management plan, not the project brief.
In summary, the purpose of a project brief is to provide a solid basis for the initiation of the project by outlining the project's objectives, scope, and key deliverables.