Time-Driven Controls in Project Management: Correct Statement

Time-Driven Controls

Question

Which statement about time-driven controls is CORRECT?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

http://prince2.wiki/Progress#Event-Driven_and_Time-Driven_Controls

A. Time-driven controls are used for monitoring the progress of work packages and management stages.

This statement is correct. Time-driven controls are used for monitoring the progress of work packages and management stages. Time-driven controls involve the use of schedules, timelines, and deadlines to track the progress of the project. This helps to ensure that the project is completed within the specified time frame.

B. Time-driven controls take place when specific events happen.

This statement is incorrect. Event-driven controls take place when specific events happen. Event-driven controls involve monitoring and controlling the project based on specific events, such as the completion of a task or the occurrence of a risk.

C. Time-driven controls are produced at the end of a stage.

This statement is incorrect. Time-driven controls are produced throughout the project, not just at the end of a stage. They are used to monitor and control the project to ensure that it stays on track and is completed within the specified time frame.

D. An exception report is a time-driven control.

This statement is incorrect. An exception report is not a time-driven control. An exception report is a document that highlights any deviations from the project plan or any issues that require attention. It is used to identify potential problems and to take corrective action to get the project back on track.