Which is a type of issue?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
In project management, an issue is a problem or concern that arises during the project execution phase that needs to be addressed and resolved to keep the project on track. Among the options provided, the type of issue is:
B. A request for change: A request for change is a type of issue that occurs when a stakeholder identifies a potential change that needs to be made to the project's scope, schedule, or budget. Requests for change can arise due to a variety of reasons, such as a change in business needs or requirements, or due to unforeseen circumstances. The project team evaluates the request for change to determine its impact on the project's objectives and makes a decision on whether to accept or reject the request.
A. A lesson: A lesson is not a type of issue, but rather an outcome of project activities that can be used to improve future projects. Lessons learned are documented and shared with the project team and stakeholders to facilitate continuous improvement.
C. An Exception Report: An exception report is a type of report that highlights any deviation from the project plan, such as missed deadlines or budget overruns. Exception reports can help project managers to identify and address issues that may impact the project's success.
D. A risk with an estimated high impact: A risk is a potential event or situation that may have an impact on the project's objectives. A risk with an estimated high impact is a type of issue that needs to be addressed and managed to minimize its impact on the project. Risk management is an important aspect of project management, and the project team should have a risk management plan in place to identify, assess, and mitigate potential risks.
In summary, out of the given options, B. A request for change is the type of issue.