During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?
Click on the arrows to vote for the correct answer
A. B. C.B.
When there is a change in the level of performance expected from the service provider during Stage 1 of the project, the following products may require updating:
A. Project Brief: The Project Brief provides a high-level description of the project objectives, scope, stakeholders, and expected outcomes. It also outlines the customer's quality expectations, which are used to measure the success of the project. Therefore, if the level of performance expected from the service provider changes, the Project Brief should be updated to reflect the new expectations.
B. Project Product Description: The Project Product Description provides a detailed description of the project's deliverables, including their quality criteria and acceptance criteria. This product is used to define the expected performance of the project's products. Thus, any change in the level of performance expected from the service provider must be reflected in the Project Product Description.
C. Quality Management Strategy: The Quality Management Strategy outlines the approach for managing quality throughout the project, including the customer's quality expectations of the project's products. Therefore, if there is a change in the level of performance expected from the service provider, the Quality Management Strategy should be updated to reflect the new expectations.
In summary, all three products may require updating if there is a change in the level of performance expected from the service provider during Stage 1 of the project. However, the Project Product Description is likely to be the most affected as it provides the detailed description of the project's deliverables and their expected performance.