Which of the following reports does not contain any information on risk?
Click on the arrows to vote for the correct answer
A. B. C. D.A.
The correct answer is D. End Stage Report.
Explanation:
In the context of project management, the various reports serve different purposes and contain different types of information.
A. Issue Report: This report contains information on the issues that have arisen during the project, their severity, and the steps taken to resolve them. While issues are not the same as risks, they can potentially become risks if they are not managed effectively.
B. Highlight Report: This report provides a summary of the progress made on the project during the reporting period, including any significant achievements or challenges encountered. While risks may be highlighted in this report if they are considered to be significant enough to affect progress, they are not a key focus.
C. Lessons Report: This report documents the lessons learned during the project, including both successes and failures. While risks are not the main focus of this report, they may be mentioned in the context of lessons learned from the project.
D. End Stage Report: This report is produced at the end of each stage of the project and provides an assessment of the stage just completed, including progress made, costs incurred, and any issues or risks encountered. While issues may be mentioned in this report, risks are not typically a key focus.
Therefore, the correct answer is D. End Stage Report.