In which strategy would the change control process be recorded?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The change control process is an essential part of project management, as it helps ensure that changes to the project are properly reviewed, assessed, approved, and implemented in a controlled and structured manner. To manage the change control process effectively, it is necessary to have a well-defined strategy that outlines the key procedures, roles and responsibilities, and tools and techniques to be used.
Out of the given options, the most appropriate strategy in which the change control process would be recorded is the Configuration Management Strategy (B). This is because the Configuration Management Strategy is concerned with identifying, defining, controlling, and verifying the components of the project and their relationships. Configuration management aims to ensure that the project components are properly managed, tracked, and reported, and that any changes to them are properly authorized, implemented, and communicated.
The change control process is an integral part of configuration management, as it involves assessing, approving, and documenting changes to the project's configuration items (CIs). The Configuration Management Strategy, therefore, provides a framework for recording and managing the change control process, including the change requests, change impact analysis, change approval, and change implementation.
While the other options, Quality Management Strategy (A), Risk Management Strategy (C), and Communication Management Strategy (D), may also involve some aspects of the change control process, they are not as directly related to the management of project components as configuration management. Quality management focuses on ensuring that the project's outputs meet the required quality standards, while risk management aims to identify, assess, and mitigate project risks. Communication management, on the other hand, is concerned with planning, executing, and controlling project communications.
In summary, the Configuration Management Strategy (B) is the most appropriate strategy in which the change control process would be recorded, as it provides a framework for managing the project components and their relationships, including any changes made to them.